Hi All,
Any ideas how to solve my problem?
Resource Joe + Damian work in a 12Hrs shift on three activities as noted in the image below. Both theses resources are assigned a Day calender in 12Hrs shift 6am to 6pm. I have used a Linear Curve for the resources.
When I assing the planned hours for Joe 12hrs (on 4th June) & 4hrs (on 5th June) = Total 16Hrs for Activity 1 for Joe, I am seeing that the planned hours are distributed linear on both shifts 8hrs + 8hrs in the Resource usage Shreadsheet.
Actually Joe works for Activity 1 for 12hrs on 4th June & 4Hrs on each Activity 1, 2, 3 on 5th June.