Hi,
Is there a setting in Primavera that will allow the resource loading (Historgram) to pickup remaining non labor units instead of remaining labor units? I'm using PL/SQL Procedure and unix scripting to load a csv file from SAP to Primavera. When the data upload is completed the activities with non labor resources was all resides in non labor unit, but when the planners scheduled those activities, the labor unit will be filled with everything with what the non labor unit have.
Activities are now scheduled