Dear PP Members,
1) How does P6 compute for the subtotal of total floats. There is a group consist of 5 activities, 4 activities having total float of 2 days each and 1 activity whose total float = -10days. The group subtotal of total float is -6days.
2) Why schedule variance is not equal to zero reference to a newly created baseline of an "in-progress project''? As far as I know, schedule variance should be zero because the baseline is just the exact copy of the current. Is there a way in P6 to set SV=0?
Thanks in advance.
Merry Christmas!!!
Jerome