Hi All,
In p6, is there any way to roll-up % complete as based on Performance? In my schedule program, some activities are costed/resourced, however, there is a Owner review period withtout respective costing.... Anayway P6 can roll progress based on a group of activities summarized by WBS? S
cenario 1, 6 activities with no resources and only half are complete, what is the base approach to get a summary of progress which ties as close as possible to EVM philsophy??
Much appreciate your advice...