Hi everyone
I have a problem with preserving dates after leveling. For example i have totally seven activity; six of them linked FS and other one is not have any successor or predecessor. Thats why two activity start with project start.
After applying the levelling, the activity which has no successor and predecessor comes after the other six activities. Problem starts here, when schedule the proggramme everything is gone back. Two activity start with project start or data date again.
How i save activity dates after levelling? It could be assign constraint or add a relation manually in order to checking dates with ms excel.
Primavera has a function to keep dates or another suggestion u know?
THANKS A LOT