Guys,
As subjected above, I had problem when I did assign actual start, the BL Start dates will change accordingly.
But this not happen to BL Finish when actual finish had been assigned.
What setting I should do guys?
As subjected above, I had problem when I did assign actual start, the BL Start dates will change accordingly.
But this not happen to BL Finish when actual finish had been assigned.
What setting I should do guys?