Hi guys,
Usually I am putting the Actual Start Date for the first time we submit the material/drawing and automatic 100%.
For approvals I will make it from the time we submit, that is 50 % and 100% until the time they approved it. I always make all the Drawings & Materials in detail to track which is which is delayed, to prevent which area/scope/activity will be affected by the delay. For me to know when I can start ordering up to delivery of materials at site. To notify immediately all responsible accounts.
How about you guys?How do you put %?is it by duration? or ...?????
Im a little confused when tracking my delays. Most of the delays I encountered are usually from Engineers/Consultant.
I always consider the Condition of Contract of the Contractor/ Employer. However, they exceed the limit and always add some additional works by the near end of the completion of the project.
Regards,
Usually I am putting the Actual Start Date for the first time we submit the material/drawing and automatic 100%.
For approvals I will make it from the time we submit, that is 50 % and 100% until the time they approved it. I always make all the Drawings & Materials in detail to track which is which is delayed, to prevent which area/scope/activity will be affected by the delay. For me to know when I can start ordering up to delivery of materials at site. To notify immediately all responsible accounts.
How about you guys?How do you put %?is it by duration? or ...?????
Im a little confused when tracking my delays. Most of the delays I encountered are usually from Engineers/Consultant.
I always consider the Condition of Contract of the Contractor/ Employer. However, they exceed the limit and always add some additional works by the near end of the completion of the project.
Regards,