Dear All,
Is there any way to show the Plan % Complete on WBS Summary Level? I have tried many ways, but it doesn’t work (the Summary is blank). I want to show the Plan % Complete from the Baseline and Current Schedule side by side in P6 in WBS Summary instead of by activity.
Those 2 schedules are already resource loaded with manhours.
Thanks.
Rifky