P3 keeps moving dates when I don’t want it to, and it creating random lag times that I don’t know how it’s coming up with the dates. Please see the pic of the tasks circled in green... these are the tasks that P3 keeps changing. Even when a task is a milestone with a date I set, P3 will change it when I hit schedule. What am I doing wrong that P3 is making all these random lag times? Pic 1 is how it looks after I hit schedule and Pic is 2 is how looks before I hit schedule.