I have just inherited a schedule, from anther company, which I am busy setting a new baseline. I have entered a new activity with a duration of 42 weeks, however when I look at the summary total, under the original duration, it shows me 4 weeks, even though the activity dates and the summary dates, show the same. I have checked the project calendars and the activity calendar, and these appear normal,