I have one acticity in my project. That activity having start to start relationship & finish to finish relationship. Its start date is project start date & finish date is project finish date. I want to distribute its cost uniformly without assigning resource curve.
How can i do that?
Can you please help me.
How can i do that?
Can you please help me.