Hello all,
I want to dynamically link an ALAP task to a buffer (an internal buffer, not a project buffer). When I do so and recalculate, the ALAP task drifts to the end of the project.
How can I dynamically link and keep the ALAP task that is a predec. of the buffer in its proper timed place?
Be well and thanks,
Eric