Hi to all.
I`m new to this forum but not to programming and scheduling.
I`ve been working with Primavera and Project for several years, but lately I got used to work with Primavera mostly.
Now I´m assigned to a project and our clients requires us to us MS Project.
In Primavera, i used to rely on a lot of information regarding predecessors and successors (I mean, relative floats, succesors relative floats, etc.).
I mean, I was able to know which predecessor was pushing an activity even when none of them where on the Critical Path.
I can´t find a way to do this in Ms Project.
Is there some sort of solution for this issue?
Thanks in advance!
PS: Sorry for my english as it is not my native language!
I`m new to this forum but not to programming and scheduling.
I`ve been working with Primavera and Project for several years, but lately I got used to work with Primavera mostly.
Now I´m assigned to a project and our clients requires us to us MS Project.
In Primavera, i used to rely on a lot of information regarding predecessors and successors (I mean, relative floats, succesors relative floats, etc.).
I mean, I was able to know which predecessor was pushing an activity even when none of them where on the Critical Path.
I can´t find a way to do this in Ms Project.
Is there some sort of solution for this issue?
Thanks in advance!
PS: Sorry for my english as it is not my native language!