I need a formula to show when the "Start" is later than the "Status Date" AND the "% Complete" equals 0...
I will apply this to a fag so that the "yes" result is returned thus showing overdue starts.
Ive tried a few but cant seem to get it working.
Cheers,
Russ.
I will apply this to a fag so that the "yes" result is returned thus showing overdue starts.
Ive tried a few but cant seem to get it working.
Cheers,
Russ.