To prepare an |EOT programme[Any Method] can you introduce project must finish by constraint in approved baseline.
If above constraint is not mentioned total float of delay event is positive which is not in favour to demonstrate the delay ?
If above constraint is not mentioned total float of delay event is positive which is not in favour to demonstrate the delay ?