Hi all,
Can somebody tell me whether there is any way to quantify % delay to number of days of delay. I have a delay in 0.79% in percent complete. Now the client want me to tell them in terms of days. The project duration is around 400 days and the critical path activities are not delayed.
cheers!
Chandan