Hi to all,
In my weekly look ahead, I have a column info as follows
1. Planned% as per baseline
2. Previous Look Ahead
3. Present % Complete
4. New Look Ahead %
I input % Comp, Actual Start, Actual Finish, and remaining duration. I run the schedule. I perform look ahead %...
Some activities will give less Look Ahead % compared to Present % Complete because P3 calculates % to complete based on remaining duration...
Can somebody helps?
Thnx,
Francis