It seems to me that Powerproject option for Reschedule/Options/Options Box – "Move part completed links" is similar to Retained Logic option in Primavera P3/P3E/P4/P5/P6/SureTrak but with the attempt to solve out-of-sequence by moving the links while Primavera products and MS Project splits the activities/tasks.
The out-of-sequence event under this Powerproject option does not show on the reports and you are left in darkness hoping the attempt gave you the correct answer.
I am not against other options, P6 provides a third option in addition to what P3 and SureTrak provides, I believe Primavera is right in keeping the warning. Does Powerprojec did what Primavera or Microsoft could not do and therefore there is no need for a warning? Is this a blooper or magic? The report should be called "Partial Warning on out-of-sequence", not to mislead you into believeng it did not happened and the solution is always correct.
Maybe the warning is somewhere else. As I have been using the software demo for a couple of days I would like to hear from those knowledgeable of the software.
Best regards,
Rafael
The out-of-sequence event under this Powerproject option does not show on the reports and you are left in darkness hoping the attempt gave you the correct answer.
I am not against other options, P6 provides a third option in addition to what P3 and SureTrak provides, I believe Primavera is right in keeping the warning. Does Powerprojec did what Primavera or Microsoft could not do and therefore there is no need for a warning? Is this a blooper or magic? The report should be called "Partial Warning on out-of-sequence", not to mislead you into believeng it did not happened and the solution is always correct.
Maybe the warning is somewhere else. As I have been using the software demo for a couple of days I would like to hear from those knowledgeable of the software.
Best regards,
Rafael