Here another issue we have come across. We need to be able to input the Physical complete % so that actual costs are based on that percentage. We want remaining duration to be manually inputted without any links to actual costs and precent complete. We have use different combinations but cannot find the right ones. Has anyone been able to find the right combination to do this?
James B.
James B.