I have and xer file that is a client project (call it Proj A) that has been imported in P6. This project originally had relationships to external projects but after importing these links no longer constrain the activities in Proj A. The dates will be reflected as it was when linked to the external projects. When I schedule, the activities that are now open-started (ie no predecessor) move to my data date loosing their original dates.
How can I schedule the newly imported project whilst keeping the original start dates in tact for the open-started activities? Is there a setting of some sort or will I have to manually put a constraint into each of the open started activities?