Dear All,
Would someone help me out for calculation of total float in different project. I have a mandateroy finish constraint in second project and have predecessor activities in first project with as late as possible constraints. P6 is showing zero total float in the second project for the activiities but showing negative total float in first project. Why? How to solve this problem.
Best regards,
Would someone help me out for calculation of total float in different project. I have a mandateroy finish constraint in second project and have predecessor activities in first project with as late as possible constraints. P6 is showing zero total float in the second project for the activiities but showing negative total float in first project. Why? How to solve this problem.