During updating of Programme of Ms Project, the total float/slack will always become Zero even the project is delay or ahead of time. It is because there is no function in Ms Project for us to key in the Overall Project Finish date. To resolved this problem, I just go to the last activity, double click it and set the deadline of the project. It seems the problem has been solved by this simple act. However, the negative float is not shown in the summary bar and the highest level of summary bar. If we cannot show the negative or positive float on the summary bar, it is quite misleading, unless I use the Finish Variace which is not so appropriate to shown the status of project in term of number of day. Anyone know how to solve this problem?
Thanks