Dear Planners
Please help me to calculate the labours/gang for following activities:
a) 75 mm thick Screed
Duration available = 4 weeks, Quantity =2116 m2
How many labours/Gangs are required to finish this job in 4 weeks?
b) 20mm thick Render over blockwork. Skim over render board
Duration available = 3 weeks, Quantity =2116 m2
How many labours/Gangs are required to complete this job in 3 weeks?
c) Flooring
5mm thick carpet tiles= 1253 m2
How many labours/Gangs are required to finish this job in 3 weeks?
5mm approx for vinyl tiles = 754 m2
How many labours/Gangs are required to finish this job in 3 weeks?
5mm approx for Matting = 109 m2
How many labours/Gangs are required to finish this job in 3 weeks?
Thanks
James