Hi,
We are currently struggling with the configuration of P6 and are looking for some guidance as Primavera have been silent on the matter.
Duration type is Fixed Duration & Units and we currently enter the following information into the plan:
● Activity percent complete
● Activity actuals (using SDK interface)
At this stage we do not want the plan to change the remaining duration as we use a global to bring back the finish date every time we move the data date (wrong I know but it is a business requirement). Effectively we use the resource histogram to manage manually pushing schedules out.
What I’m trying to find out is are we better to use Units Percent Complete or Physical Percent Complete for Activity Percent Complete Type. I would have thought Physical but I noticed the units percent complete differ from the activity percent complete if I do. Is this a problem?
Cheers,
Lorne
We are currently struggling with the configuration of P6 and are looking for some guidance as Primavera have been silent on the matter.
Duration type is Fixed Duration & Units and we currently enter the following information into the plan:
● Activity percent complete
● Activity actuals (using SDK interface)
At this stage we do not want the plan to change the remaining duration as we use a global to bring back the finish date every time we move the data date (wrong I know but it is a business requirement). Effectively we use the resource histogram to manage manually pushing schedules out.
What I’m trying to find out is are we better to use Units Percent Complete or Physical Percent Complete for Activity Percent Complete Type. I would have thought Physical but I noticed the units percent complete differ from the activity percent complete if I do. Is this a problem?
Cheers,
Lorne