Hi,
I have the following question, on which I couldn’t find and answer in google.
How to make a task with flexible duration, which will fill the gap between other 2 tasks and will automatically adjust it’s length:
Example
Task1: Deliver building material (fix start task)
Task2: Guard delivered building material (fixed units)
Task3: Build building (fix start)
So, I want Task2 to fill the gap between task 1 and task 3. I want it to adjust it’s length depending on how late task 1 finishes. So, that it will always start when task 1 is finished, and will always finish, when task 3 starts. Is it possible with MS project?
thanks
I have the following question, on which I couldn’t find and answer in google.
How to make a task with flexible duration, which will fill the gap between other 2 tasks and will automatically adjust it’s length:
Example
Task1: Deliver building material (fix start task)
Task2: Guard delivered building material (fixed units)
Task3: Build building (fix start)
So, I want Task2 to fill the gap between task 1 and task 3. I want it to adjust it’s length depending on how late task 1 finishes. So, that it will always start when task 1 is finished, and will always finish, when task 3 starts. Is it possible with MS project?
thanks