Imagine an activity, lasting 4 working days, which has a resource assigned to it. (I use this resource to track the daily cost of the activity.) This resource has a price per unit of 100 during the 1st and 2nd day, and a price of 200 during the other two days. For a budgeted quantity of four days the budgeted cost is therefore 100+100+200+200=600.
I would expect a cost loading report to show a usage per day of 100, 100, 200 and 200 (which is accurate and what I would need to show in the report). On the contrary, the report shows a usage of 150, 150, 150, 150 (600/4=150).
Is there a way to show in the cost loading report the true amount that will be spent each day for this activity ?
I would expect a cost loading report to show a usage per day of 100, 100, 200 and 200 (which is accurate and what I would need to show in the report). On the contrary, the report shows a usage of 150, 150, 150, 150 (600/4=150).
Is there a way to show in the cost loading report the true amount that will be spent each day for this activity ?