Any advise please?
I have produced an S Curve Report in P5, based on subject area Activity Resource & Role Assignments. It shows Early Target (based on Remaining Early Cost, and Late Target (based on Remaining Late Cost.
I now need to incorporate cost account costs.
The problen is, that when I run the Report Wizard (based on subject area Activity), there is no option under the Time Interval field, to show Remaining Late Cost. Only Remaining Total Cost is available (whic will be based on Early dates.)
Only way I can think of to get the Late Costs, is to re-schedule the activities to happen as late as possible (Backward Pass), but cannot find a way in P5 to do this.
Can anyone help please?
I have produced an S Curve Report in P5, based on subject area Activity Resource & Role Assignments. It shows Early Target (based on Remaining Early Cost, and Late Target (based on Remaining Late Cost.
I now need to incorporate cost account costs.
The problen is, that when I run the Report Wizard (based on subject area Activity), there is no option under the Time Interval field, to show Remaining Late Cost. Only Remaining Total Cost is available (whic will be based on Early dates.)
Only way I can think of to get the Late Costs, is to re-schedule the activities to happen as late as possible (Backward Pass), but cannot find a way in P5 to do this.
Can anyone help please?