In one of the running project, the contractor has accelerated the works him self without any instruction nither from the client nor from the engineer.
The contractor was planning to complete some particulare activites ahead of time in order to demobilize the resources allocated for these activities from this contract and mobilized in another new contract.
The weekly up dated progress reports were showing that the contractor actual progress is ahead of program .
Sudenly the employer has issued some additional works which have no impact on the recent status of the project and can be completed within the original contract period but it will prevent the contractor from demobilizing the resources as he was entrnaly planned.
does the contractor has a right to claim for EOT or not and what are the justifibale reasons.
Please advise me.
The contractor was planning to complete some particulare activites ahead of time in order to demobilize the resources allocated for these activities from this contract and mobilized in another new contract.
The weekly up dated progress reports were showing that the contractor actual progress is ahead of program .
Sudenly the employer has issued some additional works which have no impact on the recent status of the project and can be completed within the original contract period but it will prevent the contractor from demobilizing the resources as he was entrnaly planned.
does the contractor has a right to claim for EOT or not and what are the justifibale reasons.
Please advise me.