I am looking at ahousing development in Scotland which has about 60 houses on the site.
I expect one to take 18-20 weeks to construct, does anyone have a general rule for how the programme can roll from the first house, is it 1 per week after that or 2 per week or is this too quick,
would appreciate any guidance.
Thanks