our plant works in two shifts , 1st shift from 6:00 AM to 6:00 PM ( with break at 12:00 to 1:00 PM ) and 2nd shift from 6:00 PM to Next day 6:00 AM ( with break from 12:00 to 1:00 AM )
Can someone tell me how to enter these timing in " change project timing " window. Because if i enter these timing it gives the message as "end time has to be later than start time."
Can someone tell me how to enter these timing in " change project timing " window. Because if i enter these timing it gives the message as "end time has to be later than start time."