Hi Planners..
Its me again, with another question.. *OH NO!!! EVERYONE HIDE!!!*
LOL.. Yea, Ive got issues.. I know..
Anyways, Ive made this file in MSP and inserted sub-projects thats linked to other files in my system. Basically my objective is to provide a snapshot of all projects running in the firm that I work in.
The problem is that the resources are broken up into the different subprojects. What Im after is a cumulative usage of the resources for the whole subprojects. Is this possible and how would I be able to do it?
Ive tried another way like instead of inserting subprojects, i used copy/paste from each individual projects. This gives me what I want in terms of the cumulative resource usage, but the file doesnt automatically update itself like it does when I use subprojects.
Thanks Planners!
M
Its me again, with another question.. *OH NO!!! EVERYONE HIDE!!!*
LOL.. Yea, Ive got issues.. I know..
Anyways, Ive made this file in MSP and inserted sub-projects thats linked to other files in my system. Basically my objective is to provide a snapshot of all projects running in the firm that I work in.
The problem is that the resources are broken up into the different subprojects. What Im after is a cumulative usage of the resources for the whole subprojects. Is this possible and how would I be able to do it?
Ive tried another way like instead of inserting subprojects, i used copy/paste from each individual projects. This gives me what I want in terms of the cumulative resource usage, but the file doesnt automatically update itself like it does when I use subprojects.
Thanks Planners!
M