How to measure the actual progress for varying qty.
For excample in one piping installation activity contract says 100LM to install, based on that I have planned progress for each week, as the activity progress i feel that the qty may reach only 50LM, in that case my actual progress is very much behind the planned qty (and visa versa).
thanks in advance