Dear Planner
Ive faced a problem, I would be really glad if you help me to solve it.
I should compare actual time schedule with baseline time schedule, my problem is:
in "BL Cost % Complete", cost % complete is not roll up for summary activity (in WBS level, it doesnt show total) even I restored the baseline it worked well and all cost % complete was rollup but when I mark it as baseline again it is not roll up in summary level (total was not shown!)
Ive tried many ways such as changing data date,… but they couldnt help me!
How can I make primavera sums and shows total cost % complete in "BL cost % complete" for summary task?
Thanks in advance
Amir
Ive faced a problem, I would be really glad if you help me to solve it.
I should compare actual time schedule with baseline time schedule, my problem is:
in "BL Cost % Complete", cost % complete is not roll up for summary activity (in WBS level, it doesnt show total) even I restored the baseline it worked well and all cost % complete was rollup but when I mark it as baseline again it is not roll up in summary level (total was not shown!)
Ive tried many ways such as changing data date,… but they couldnt help me!
How can I make primavera sums and shows total cost % complete in "BL cost % complete" for summary task?
Thanks in advance
Amir