Hi All,
I have an issue here.
I’m working in some houses schedule; I create the schedule with estimated durations, and also the lump sum amounts that each activity carries.
The duration of one of the houses is 90 days, and I’m doing the update at day 60. All the activities are on track (with very little differences in the duration), the amount spent up to date according to the resource loading is 58%.
My problem here is that the schedule summary bar shows only 53%.
Is any other factor that primavera need to calculate a percentage of completion accurate?
Thanks
Juan
I have an issue here.
I’m working in some houses schedule; I create the schedule with estimated durations, and also the lump sum amounts that each activity carries.
The duration of one of the houses is 90 days, and I’m doing the update at day 60. All the activities are on track (with very little differences in the duration), the amount spent up to date according to the resource loading is 58%.
My problem here is that the schedule summary bar shows only 53%.
Is any other factor that primavera need to calculate a percentage of completion accurate?
Thanks
Juan