Hi, Ive been getting errors when loading resources into a MS Project schedule. Calendar is configured as 8 hours/day from Monday through Friday. Then, I input taks and their respective durations (in days). Later on, I create my resources and load them into the tasks. Work Effort field (man-hours) sometimes get wrong calculations and sometimes the software splits the bar (with dots between the split bars). Could anyone tell me if Im doing something wrong or maybe I need to setup something or whatever? I will appreciate any help on this issue. Thank you.