The % complete figure that is calculated for the project when using ms project does not correlate to the % i get when i divide the man hours used by the total man hours for the project. (For eg MSProject calculated total % complete = 20% whereas Used Man Hours / Total Man Hours = 17%)
Has anyone got any suggestions?