Planners - please help
I have been asked to update an already started project plan to detail personnel resources. It has a task heading of Company Resourcesand then 30 sub tasks each being a task to be done. My problem is that as I move down the list and change start and finish dates for some reason the dates of other tasks are being changed? Can you advise on what the contraint type should be? Non of the tasks are linked? I would be most grateful for any advice.
Dave
I have been asked to update an already started project plan to detail personnel resources. It has a task heading of Company Resourcesand then 30 sub tasks each being a task to be done. My problem is that as I move down the list and change start and finish dates for some reason the dates of other tasks are being changed? Can you advise on what the contraint type should be? Non of the tasks are linked? I would be most grateful for any advice.
Dave