Hi all,
We have many projects. Say P1, P2 and P3...and so on.
I have created resource called MA= Mason. I have 2 masons available.
How to set availability of 2 masons. I do not want to create MA1 and MA2. Istead, I want to show under MA manpwoer available is 2.
When I create and level schedule, if total project requriement for masons in 4, then either I can inform shortage of manpower or delay in schedule or look for alternate action.