I dont understand the figures mainly.
Cost wise theres 5 activities within the WBS element with a combined budget of £525k, the individual physical percent completes give an earned value of £280k or 53%.
Manhour wise the activities have 850 hours between them, 200 have been progressed as earned giving 24%.
Using Performance percent complete to roll up the figures gives me a value of 2.5% progress for the WBS element, I dont have much hair to tear out and I just dont get it?!
Any ideas gratefully recieved...
Cost wise theres 5 activities within the WBS element with a combined budget of £525k, the individual physical percent completes give an earned value of £280k or 53%.
Manhour wise the activities have 850 hours between them, 200 have been progressed as earned giving 24%.
Using Performance percent complete to roll up the figures gives me a value of 2.5% progress for the WBS element, I dont have much hair to tear out and I just dont get it?!