I have gathered from Construction Managers (Saudi experience) is that in al-Jubail area 1-2 cumulative days/month are lost due to high speed winds/ Sand Storms during April-May.
Has anyone done analysis on effect of wind on Construction work specially Structural erection/ Piping erection work at high elevations.
What is the effect of the same on productivity at ground level?
Is this normally taken care during planning stage in these areas?
Regards
Dattatreya
Has anyone done analysis on effect of wind on Construction work specially Structural erection/ Piping erection work at high elevations.
What is the effect of the same on productivity at ground level?
Is this normally taken care during planning stage in these areas?
Regards
Dattatreya