Schedule Risk analysis itself is a complicated subject full of probabilities & statistics.
A robust schedule is a mandatory prerequisite for such an analysis.
A schedule where durations are governed by quantities (productivity).
But when it comes to activity relationships, things become really complicated. We can end up with number of possibilities between two activities.
E.g Piping Prefab & erection & their relationship (SS/FF).
At the start of the Project/Proposal stage how should we take care of these uncertainities in relationships?