I’ve tested the following scenario on different scheduling platforms and seen several different answers. What would you expect?
Task 1 (10 hrs) 24hrs/day calendar
Task 2 (4 hrs) 8hrs/day calendar Preds=1FF
Task 3 (1 hrs) 24hrs/day calendar Preds=2
At what hour would you expect Task 2 to end? Task 3 to start?