Hi,
With version 3.50 we notice that the ES/EF dates with LOE activities do not reflect the correct schedule spans of the underlying task-dependent predecessors after resource leveling. Is this a P3e bug in v3.50? Is there a work-around or has it been fixed in v3.51 or v4.0?
Cheers
With version 3.50 we notice that the ES/EF dates with LOE activities do not reflect the correct schedule spans of the underlying task-dependent predecessors after resource leveling. Is this a P3e bug in v3.50? Is there a work-around or has it been fixed in v3.51 or v4.0?
Cheers