Could someone clarify? the significance between the usage of Activity Codes and Activity Ids in the Activity Codes Dictionary in Primavera Project Planner Schedule.
I understand that of defining activity IDs in the codes dictionary would be easy to reduce our work load to certain extent.
for Example defining these items in the activity codes dictionary,
SUBP - as SubProject
PC - as Price Centre or Cost Code
In the "Values" dialogue box, we can define
RP- Rail Project (as sub package)and
01 as cost code for design works etc....
02 as cost code for construction of foundation works etc
hence in the activity ID area we can start the ids with RP01... for relevant activities.
hence it would save our time of assigning activity codes for each activities(if it belongs to the same group for example), hence we can straightaway organise the activities
in the organisation area.
but i would like to explore other benefits than the one which i have mentioned above. so please mention other benefits if any on the above subject.
I understand that of defining activity IDs in the codes dictionary would be easy to reduce our work load to certain extent.
for Example defining these items in the activity codes dictionary,
SUBP - as SubProject
PC - as Price Centre or Cost Code
In the "Values" dialogue box, we can define
RP- Rail Project (as sub package)and
01 as cost code for design works etc....
02 as cost code for construction of foundation works etc
hence in the activity ID area we can start the ids with RP01... for relevant activities.
hence it would save our time of assigning activity codes for each activities(if it belongs to the same group for example), hence we can straightaway organise the activities
in the organisation area.
but i would like to explore other benefits than the one which i have mentioned above. so please mention other benefits if any on the above subject.