Dear All,
Could you please advise how to re-schedule the progress activity in MS Project? I want the progress will override the logic.
The case is the logic is not valid anymore due to some reason.
In Primavera, there is choice as follow :
- retained the logic or
- progress override (the logic).
- actual date
Thanks
Tandyo