This is my first time involved in this forum. I am now working for a Construction Company in Indonesia.
I have a problem regarding the Weigth Factor for EPC project (oil & gas )in preparing S-Curve by Excel. I used to utilize the MONEY (US$) as weight factor for each activity or WBS, but now my boss want to utilize the MANHOURS as weight factor.
My question is which one the rigth one to be used as weight factor between MONEY and MANHOUR for EPC (Engineering, Proc, Constr.) project. As far as Iknow, MANHOUR is only applicable as weigth factor for Engineering Project.
I am looking forward your advices. Thank you.