Hi,
Earlier I used Asta Powerproject to make "takt plans". Powerproject enabled me to split the gantt bar and connect the start the succeeding activity after gantt split. I have not been able to figure out how to do this n OPC. Is anyone familiar with how to do this?
Here is a link to a typical "takt plan": https://images.app.goo.gl/kfJPgQgSRGSRnYbm8 [1]if you want to see the concept.
Best regards
Roy