Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Quick Update - a process that explains how to update Primavera schedules in quick time

"Quick Update" is a process that explains how to update Primavera schedules in quick time.

This presentation will illustrate how to update a schedule in 8 short stages.

  1. Create a Baseline
  2. Switch ON auto schedule
  3. Ensure that Baseline Bar is switched ON
  4. Apply Actuals
  5. Move Data Date Forward
  6. Review IN PROGRESS activities - Update Remaining Duration/Finish Dates
  7.  Review progress of activities on Data Date - Update Start Dates
  8. Switch OFF auto schedule

Author:- David R.V.Forrest

ADVICE: You need to be a Guild Member to view / download the articles in the Guild's Library.