Quick Update - a process that explains how to update Primavera schedules in quick time
"Quick Update" is a process that explains how to update Primavera schedules in quick time.
This presentation will illustrate how to update a schedule in 8 short stages.
- Create a Baseline
- Switch ON auto schedule
- Ensure that Baseline Bar is switched ON
- Apply Actuals
- Move Data Date Forward
- Review IN PROGRESS activities - Update Remaining Duration/Finish Dates
- Review progress of activities on Data Date - Update Start Dates
- Switch OFF auto schedule
Author:- David R.V.Forrest