Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Sub-Portfolio/Programme Contingency Reserve = Project Management Reserve?

No replies
Maxim Dr
User offline. Last seen 5 years 44 weeks ago. Offline
Joined: 25 Jul 2017
Posts: 6
Groups: None

Hello all,

 

We with colleagues are currently trying to sort out whether the Reserve held at the Programme or Sub-portfolio level can be deemed the management reserve of the project?

We are a big organisation and there is a very large portfolio of multi-million projects. Some projects get closed and there is a budget left which is transferred to the Programme or Sub-portfolio Reserve.

Sub-portfolio may have a number of projects, say 15-20 projects, and the Sub-portfolio reserve has been accummulated as a result of closed projects if the actual total cost was less than the BAC.

If for example, an active project is short of money and the management decides to allocate the funds from Sub-portfolio reserve to the project. Can we call this sub-porfolio reserve a management reserve for projects or does a management reserve of a project has to be specific to that project and agreed in advance?