Importing 3 Point Estimates into Pertmaster

No replies
Dave Jones
User offline. Last seen 11 years 20 weeks ago. Offline
Joined: 4 Sep 2009
Posts: 11
Groups: None
I am using the latest versions of P6 and Primavera Risk Analysis 8.6 (formerly Pertmaster).

For each resource assignment, I have a 3 point estimate for the effort .. ie min 6 hrs, likely 12 hrs, max 23 hrs.

There are multiple resource assignments per activity.

How cam I import this data into Pertmaster?

The standard Primavera/Pertmaster integration only allows either:
a) resources to be imported (but no 3 point estimates), or
b) summarised costs with 3 point estimates at the activity level.

Could a Macro importing from an excel file be a possibility? Or are there any other options?